Upgrades to Lift Station Pumps A and B

 

Evaluate System
Completed: Oct 15, 2020
Oct 10 2019
Moratorium
Completed: Apr 8, 2021
Apr 8 2021
Present Solution
Completed: Apr 8, 2021
Apr 8 2021
Colleton County Funding
Completed: May 4, 2021
May 4 2021
Engineering
Completed: May 11, 2021
May 11 2021
RIA Grant Application Submission
Completed: Sep 13, 2021
Sep 13 2021
RIA Grant Award
Completed: Nov 4, 2021
Nov 7 2021
Kick off Meeting with RIA
Completed: Nov 23, 2021
Nov 23 2021
Notice to Proceed RIA
Completed: Nov 23, 2021
Nov 23 2021
Permit Issued
Completed: Dec 31, 2021
Nov 30 2021
Project Bid
Completed: Jan 27, 2022
Dec 15 2021
Bids Due
Completed: Mar 2, 2022
Mar 02 2022
Recommendation of Award
Completed: Jun 6, 2022
Jun 06 2022
Begin Construction Pump B
Dec 11 2022
Substantial Completion Pump B
Apr 13 2023
Notice to Proceed Pump A
Jan 22 2024

Last year the Town contracted with American Engineering Consultants to perform  the sewer system modeling and capital improvements program.  This involved field investigations and condition assessment of the system.  American Engineering conducted monitoring to establish wet weather and summer peaking factors to be used in the hydraulic model calculation.  This involved installing data loggers in all 13 lift stations.  Monitoring took place over 6 months.  A hydraulic model of the system was created using GIS data obtained from the Town.    Using field evaluations and the hydraulic model, American Engineering created a list of critical sewer system areas and improvement recommendations.

After consulting with the engineers about the collection system and issues identified, a sewer tap moratorium was issued in March 2021.  In April 2021, American Engineering presented their findings and recommended solutions for the sewer system. 

Phase I of the proposed recommendations include:

  • Upgrade Pump Stations A and B with larger pumps (keep centrifugal type pumps)
  • New Variable Frequency Drives and Controls at both pump stations
  • No new forcemain to be installed – no easements or construction outside of pump station required – Short Construction Duration

This recommendation provides approximately 70 Residential Equivalent Units (taps) each added to Pump Station A and  Pump Station B and approximately 80 Residential Equivalent Units added to Pump Station C over the number of current connections.

The project cost $860,000. 

$112,000 Engineering (Funded)

$748,000 Construction (Seek $500,000 grant from SC Rural Infrastructure)

 

 

Project Manager-Iris Hill

American Engineering Consultants

$61,452.00-Sewer System Modeling and Capital Improvements Program- Work Authorization 14 Council approved October 10, 2019

$112,000-Upgrades to Pump Stations A and B-Work Authorization 15  approved by Council  May 13, 2021. 

Colleton County Capital Project Sales Tax provided the $112,000 in funding for the engineering phase. 

SC Rural Infrastructure Authority - Jackie Mack Senior Program Mgr

The SCRIA notified the Town on November 1, 2021 that the $500,000 grant was approved. Grant #R-22-1305

Documents

Work Authorization 14
Work Authorization No. 14
2021 Edisto Beach Sewer System
2021 Town of Edisto Beach Sewer System
RIA Grant Application
RIA Grant Application for Lift Stations A & B
RIA Grant Application
South Carolina RIA Grant Award
RIA Grant Application
RIA Kickoff Meeting Notes November 23, 2021
RIA Grant Application
SCRIA Notice to Proceed Grant #R-22-1305

Project Updates

South Carolina Rural Infrastructure Authority Grant Application
Wednesday, September 8, 2021

The SC Rural Infrastructure Authority Grant Application has been completed and will be submitted on September 13, 2021 for $500,000.  The local match is $248,000.  This grant application is for the construction of Lift Station A and Lift Station B pump upgrades that will allow the Town to lift the moratorium. 

Colleton County Funds Engineering
Tuesday, May 4, 2021

Colleton County Council approved funding in the amount of $112,000 for engineering the upgrades to pump stations A and B. 

Pages