Fire Hydrant Refurbishment

 

Project Commencement
Completed: Apr 1, 2021
4/01/21

The Edisto Beach Fire Department is refurbishing 12 fire hydrants this year.  The process includes removing the old paint and rust from the hydrants using a variety of mechanical tools, followed by replacing any needed hardware, such as rusty bolts.  Next, the hydrants are painted with primer paint and then finished with a coat of fresh red paint.  The Fire Department is completing this project in-house with the assistance of the Town's Utility Department.

Project Updates

Hydrant Painting Project Update
Tuesday, October 12, 2021

3804 Scott Creek Drive (Possible replace)

  1. Poor condition
  2. Bolts need to be replaced.

 Island Cove (poor condition), (COMPLETED)

  1. Stripped 04/13/2021
  2. Primed 04/14/2021
  3. Serviced 10/22/2021
  4. Repainted 10/22/2021

 Marsh Point (pool house SE door ramp), (Poor Condition)

  1. Dug out 04/05/2021
  2. Stripped 04/05/2021
  3. Primed 04/08/2021
  4. Needs bolts replaced.

 146 Palmetto Blvd. (beach access #2), (Bad condition), (COMPLETED)

  1. Dug out 04/21/2021
  2. Stripped 04/21/2021
  3. Primed 04/23/2021
  4. Painted 10/22/2021

 Beach access #4, (Possible replace), (Poor condition), (COMPLETED)

  1. Stripped 05/14/2021
  2. Primed 04/14/2021
  3. Painted 10/22/2021

 711 Palmetto Blvd. (Bad condition)

  1. Stripped 04/30/2021
  2. Primed 05/07/2021

 676 Buoy Street (Fair condition)

 420 Palmetto Blvd. (Fair condition), (COMPLETED)

  1. Stripped 10/22/2021
  2. Primed 10/22/2021
  3. Painted 10/22/2021

 1617 Lybrand Street (Fair condition)

 1501 Dorothy Street (Fair condition)

 2306 Murray Street (Fair condition)

 2002 Myrtle Street (Fair condition)

 2405 Palmetto Blvd (Fair condition)

 Holmes St. and Murray St. behind Fire Station (Fair condition), (COMPLETED)

  1. Stripped 10/22/2021
  2. Primed 10/22/2021
  3. Painted 10/22/2021

 State Park entrance across from Food Lion (Fair condition), (COMPLETED)

  1. Stripped 10/22/2021
  2. Primed 10/22/2021
  3. Painted 10/22/2021

 520 Palmetto Blvd. (Fair condition), (COMPLETED)

  1. Stripped 10/22/2021
  2. Primed 10/22/2021
  3. Painted 10/22/2021

 110 Palmetto Blvd. (Fair condition), (COMPLETED)

  1. Stripped 10/22/2021
  2. Primed 10/22/2021
  3. Painted 10/22/2021

 128 Palmetto Blvd. (Fair condition), (COMPLETED)

  1. Stripped 10/22/2021
  2. Primed 10/22/2021
  3. Painted 10/22/2021

 520 Palmetto Blvd. (Fair condition), (COMPLETED)

  1. Stripped 10/22/2021
  2. Primed 10/22/2021
  3. Painted 10/22/2021

 

Beach Access 2 Hydrant
Wednesday, June 30, 2021

Beach Access 2 Hydrant Before

Beach Access 2 Hydrant Primed

In-House Refurbishment 711 Palmetto Blvd
Wednesday, June 30, 2021

After the initial work was contracted, the Fire Department purchased equipment to perform this work in-house.  They established a priority list of hydrants for work.

 

 

Hydrant at 711 Palmetto Blvd Before

Chief Conley Refurbishing Hydrant

Primed Hydrant

 

Hydrant Refurb Beach Access 4
Wednesday, June 30, 2021

Beach Access 4

 

Chief Conley Beach Access 4 HydrantBeach Access 4 Hydrant

 

Rust Removal Before and After Photos
Wednesday, April 14, 2021

Before and After Rust Removal

BeforeAfter