Billow Street/Arc Street Drainage Project

 

RFQ 2019-07
Completed: Nov 5, 2019
Nov 5 2019
Presentation by Firms
Completed: Jan 22, 2020
Jan 22 2020
Award by Council
Completed: Feb 13, 2020
Feb 13 2020
Contract Negotiated
Completed: Mar 24, 2020
Mar 24 2020
Work Authorization Proposals
Completed: Apr 30, 2020
Mar 24 2020
Work Authorization Council Approval
Completed: May 14, 2020
May 14 2020
Notice to Proceed
Completed: May 15, 2020
May 15 2020
Data Logger Install on Lagoon
Completed: Aug 25, 2020
Jun 20 2020
Davis & Floyd Council Presentation
Completed: Nov 12, 2020
Nov 12 2020
Davis & Floyd Council Presentation
Completed: Mar 11, 2021
Mar 11 2021
American Rescue Plan Funding
Completed: Oct 19, 2021
Jul 01 2021
Request for Bids
Completed: Dec 2, 2022
Sep 09 2022
Project Awarded
Completed: Dec 8, 2022
Dec 8 2022
Notice to Proceed
Jan 20 2023
Substantial Completion
Jan 11 2024

In 2014, the South Carolina Department of Transportation and the Town implemented the first phase of a drainage plan in this area.  Crossdrains were installed across Palmetto Boulevard and positive flow drainage was established to the outfall at the end of Billow Street.  However, to improve drainage, ditches were deepened.  Phase II of this project is to determine additional improvements to drainage in this area which may include installation of pipes.  If so,  plans will be made to implement improvements to the ditches in the area.  

Project Manager-Iris Hill

Davis and Floyd - Ryne Phillips Project Manager

Documents

Davis and Floyd Work Authorization

Project Updates

Presentation to Council
Monday, October 26, 2020

Davis and Floyd will present findings to Council on November 12, 2020.

Arc Street Drainage Ditches
Thursday, August 15, 2019

Arc Street Drainage Ditches