Hurricane Dorian Repair

Milestones

Project Description

Hurricane Dorian impacted the shoreline of Edisto Beach around 5–6 September 2019. The storm produced high water levels (surge), increased wave energy, and tropical-storm-force winds as it passed inland. Offshore wave heights were measured at 7.5 meters (m) (~25 feet [ft]) during the storm. The storm passed just offshore of Edisto Beach, with the eye located about 70 miles offshore at 1200 UTC on 5 September. At that time, Dorian was a Category 3 storm with ~115 mph winds.

To restore the sand quantity lost from the project area, the Town of Edisto Beach intends to add the same quantity of sand to the beach using sand imported from an upland source.  This will require trucking in the sand from an upland source using beach compatible sand and adding it to the areas that were eroded. 

The total volume loss for the storm (34,383 cy) includes background erosion. CSE stated that the “project area averages a loss of 41,278 CY per year, as determined from total losses between 2006 and 2015. Applying this value over five weeks (the interval between pre- and post-storm surveys), yields a five-week loss of 3,969 CY. Subtracting the background erosion from the measured losses provides a total storm-induced loss of 30,414 CY.”

The total incident-related sand loss for the Project is 30,414 CY.

The estimated project cost is $678,280.

If approved by FEMA, they would provide reimbursement of 75% or $508,710. 

ATAX approved funding $320,000. 

Project Resources

  • Project Manager-Iris Hill

    This is a FEMA 4464-DR-SC project.  Obligated Funds $678,280.  ATAX Funds approved $320,000

  • Coastal Science and Engineering-Steven Traynum

    Contract Amount $61,000

  • GreenWave Contracting, Inc.

    Contract Amount $779,410 Awarded by Council January 14, 2021

Project Updates

  • Post Construction Letter from Coastal Science and Engineering

  • Project Update February 10, 2021

    The project is progressing as scheduled.  The contractor worked later than normal last night in order to move sand around Coots during low tide.  They are not placing sand under the pier due to safety and liability concerns.  The contractor should be finished with the front beach work this week and move to Beach Access 28 later this week. 

    On February 5th there were 57 loads of sand placed on the beach.

    On February 8th there were 70 loads of sand placed on the beach. 

    On February 9th there were 56 loads of sand placed on the beach. 

    Project February 8, 2021

  • Project Update February 3, 2021

    The project is moving along quickly.  The contractor is working between groins 3 and 4. 

    Yesterday they placed 1,312 cubic yards of sand between groins 3 and 4.  On February 1, 2021 they placed 1,520 cubic yards of sand between groins 3 and 4 and January 29, 2021, they placed 1,408 cubic yards of sand between groins 4 and 5.  

    The contractor has started sweeping the road again after resolving equipment issues.  The Town has requested that the scarped areas be tapered daily and that they complete the dune work in each area daily before moving to the next area.  

    Next week the contractor should be working around beach access 28.  This will increase traffic on Palmetto Blvd. 

    Working face of beach nourishment projectScarping of newly nourished area

  • Update

    As of today, the contractor has placed approximately 8,064 cubic yards of sand on the beach.   

    Progress January 28, 2021Progress Photo

    Progress Photo

  • Project Update

    Yesterday construction commenced.  The contractor delivered a total of 71 loads of DHEC approved sand running 12 trucks.  The sand has a reddish hue which is due to a higher iron content then dredged sand and should become lighter over time.  

    Dump Truck placing sand on beachSand Being Placed on Beach Nourishment Beach Access 4Nourishment Beach Access 4

     

  • Construction Commenced

    Green Wave Contracting began the renourishment project today.  They are staging at Beach Access 1 and hauling sand along the beachfront.  Construction at Beach Access 1

  • Project Award

    This Thursday, Council voted to award the spot nourishment contract to Greenwave Contracting, Inc.  This is to replace sand lost during Hurricane Dorian.  The volume of sand is regulated by FEMA so the beachfront will not look like it did after the 2017 nourishment. 

    We have a March 30, 2021 deadline with FEMA.  The contractor has begun mobilizing equipment at beach access 1 and will begin trucking sand on Tuesday, January 19, 2021. 

    The areas  impacted are the 100-300 blocks of Palmetto Blvd and the 2800 block of Palmetto.  The contractor will be running 10 truck daily and estimates 50 loads per day.  The hours of operation are Monday through Friday 7 am to sundown.  They will start on the north end of the beach around the 400 block.  

     The project involves trucking in sand.  Sand will be brought to the beach accesses and then moved along the beachfront by heavy equipment to rebuild portions of the dune and berm or beachfront.  The sand consistency will be finer than dredged sand.    This will impact traffic on Palmetto Blvd.  The project calls for 30,414 cubic yards.  Dump trucks typically carry 10-14 cubic yards so there will be around 2,143 total truck-loads.

    The dump trucks and heavy equipment have backup alarms which is a high pitched alarm sound. Noise will be an issue that cannot be avoided.   

    After the project is completed, SCDOT will resurface Palmetto Blvd  from Dorothy to the Pavilion.  That process should only take a couple of days.  The same as when they resurfaced from Yacht Club Road to Dorothy this past year. 

  • Project Costs

    The project costs came in higher than estimated by FEMA so the Town has made a funding adjustment request. 

  • Funding Obligated

    The Town was notified December 4, 2020 that the project funding had been obligated.  This means FEMA will reimburse 75% of the approved project cost to the Town. 

  • Project Bid

    The project has been advertised for bid.  Bids are due December 30, 2020. 