Milestones
Project Description
Many Town unpaved roads are in need of additional road material to mitigate persistent flooding. This may consist of additional shell sand, slag or 57 stone.
Project Updates
Project Complete
All work has been completed.
Dolphin Street Update
The contractor was making good headway on the road stabilization when Edisto Beach received over 7 inches of rain. This has created a mess and the contractor is working on repairing damages. Please use caution when using this road until the road is stabilized.