Milestones
Project Description
The end of Yacht Club Road pavement and bike path are in disrepair. There is also a drainage system that was impacted from the previous years storms. Town staff will be working on the drainage and the pot holes on Yacht Club Road. Bids are being acquired for repaving the end of the road as well as the bike path.
Project Resources
Bob Doub, Project Manager
Action Services, Inc.-$36,937
Project Updates
Project Completion
This project was completed on October 18, 2019
Project Start
Action Services started the project on October 15, 2019
Notice to Proceed
The business license was obtained and notice to proceed was issued on September 23, 2019. Robert Doub is overseeing the project for the Town.
Contract Execution
The signed contract was received with all backup.
Notice to Award
Notice to award was mailed on September 13, 2019 with the contract.
Project Award
Council awarded the contract to Action Services, Inc. at a cost of $36,937 to be funded from a transfer from general fund contingency to general fund capital projects.
Project Update
Bids were received on August 22, 2019. The Bid Tabulation has been included under associated files. The award is scheduled for Council consideration on Sep 12, 2019.